Onboarding Activities and Due Dates
Mohawk
Niagara
Complete Implementation Form - Sept 30
Confirm Alma Primo CNAME - Oct 14
Complete GTKA Training - Oct 24
Complete 3rd Party Integrations Form - Oct 28
Complete First Draft ILS Data Extracts - Nov 11
Complete First Draft Field Mapping Form - Nov 11
Complete First Draft Migration Form - Nov 11
Complete First Draft P2E Input Files - Nov 11
Complete First Draft eResource Activation Form - Nov 11
N/A
Complete Authentication Form - Nov 18
Complete ILS Revised Data Extracts - Dec 5
Complete Revised Field Mapping Form - Dec 5
Complete Revised Migration Form - Dec 5
Complete Revised P2E Input Files - Dec 5
Complete Revised eResource Activation Forms - Dec 7
Complete 360 Extract Report (360 Customers) - Dec 7