Introduction
The Page 1+ Implementation Project involves migrating participating libraries from their existing ILSs to a shared Library Services Platform (LSP), specifically Ex Libris Alma & Primo. Learn more about the project and Page 1+.
Key Details
Current Phase: Build
Go Live Date: July 26, 2022
Project Status: ON TRACK
Project phases: Get Ready, Onboarding, Define, Build, Deploy
Stakeholders: 18 participating colleges, OCLS, Ex Libris (vendor)
High-Level Project Phase Timeline
Important Dates
Event | Date |
---|---|
Configuration Freeze for Alma | ~June 28 |
Cutover Start | July 3 |
Full Alma & Primo Lockout | July 8 |
Cutover Alma Data Release/Review/Acceptance | July 21-22 |
Fulfillment Cutover (FCO)
| ~July 22-25 July 22 July 25 |
Cutover Primo Release/Review/Acceptance | July 25 |
Go Live | July 26 |
Activities Overview by Phase
Onboarding | Define | Build | Deploy |
---|---|---|---|
|
|
|
|