Introduction

The CLSP Implementation Project involves migrating participating libraries from their existing ILSs to a shared Library Services Platform (LSP), specifically Ex Libris Alma & Primo. Learn more about the project and the CLSP.

Key Details

  • Current Phase: Build

  • Go Live Date: July 26, 2022

  • Project Status: ON TRACK

  • Project phases: Get Ready, Onboarding, Define, Build, Deploy

  • Stakeholders: 18 participating colleges, OCLS, Ex Libris (vendor)

High-Level Project Phase Timeline

Sep2021OctNovDecJan2022FebMarAprMayJunJulCurrent Status
Project Phases

Onboarding

Build

Deploy

Define

Get Ready

Priority Tasks

Task

Due Date

Completing initial review of Mapping Form

May 20

Complete Scheduled Jobs Spreadsheet

May 31

Important Dates

Event

Date

ILS Technical Freeze
Any data changes must be complete before this date

May 20

Final Data Extracts

June 6

Migration, Mapping, Link Resolver/360/P2E Forms

June 21

Configuration Freeze for Alma
No further configuration changes in Alma

~June 28

Cutover Start

July 3

Full Alma Lockout
No access to Alma test environments - can use sandboxes

July 8

Cutover Data Release/Review/Acceptance

July 21-22

Fulfillment Cutover (FCO)

  • ILS Circulation Freeze/Extract

  • FCO Data Release/Review/Acceptance

~July 22-25

July 22

~July 24-25

Go Live

July 26

Activities Overview by Phase

Onboarding

Define

Build

Deploy

  • Project overview meeting

  • Access to Sandbox

  • Getting to Know Alma eLearning

  • 3rd party integration readiness

  • Data migration readiness

  • Kickoff meeting

  • Confirm project plan

  • Project status calls

  • Alma Essentials eLearning

  • Migration & configuration inputs

  • Migration test load

  • Environment delivery

  • Workflows & functional review

  • Functional calls

  • Advanced eLearning

  • Alma workshop

  • Discovery interface setup

  • GO LIVE readiness checklist

  • 3rd party integration set up

  • Administration certification

  • Library staff training

  • CUTOVER
    (freeze and load)

  • GO LIVE

  • Functional & project status calls

  • Switch to support readiness

  • Switch to Support