Introduction
The CLSP Implementation Project involves migrating participating libraries from their existing ILSs to a shared Library Services Platform (LSP), specifically Ex Libris Alma & Primo. Learn more about the project and the CLSP.
Key Details
Current Phase: Build
Go Live Date: July 26, 2022
Project Status: ON TRACK
Project phases: Get Ready, Onboarding, Define, Build, Deploy
Stakeholders: 18 participating colleges, OCLS, Ex Libris (vendor)
High-Level Project Phase Timeline
Priority Tasks
Task | Due Date |
---|---|
Complete SIS and Authentication | April 29 |
Confirm extract preferences for OCLS/Complete Cutover Survey | April 29 |
Symphony colleges - Complete Go Live Readiness Checklist | April 29 |
Non-Symphony colleges - Complete Go Live Readiness Checklist | May 10 |
Important Dates
Event | Date |
---|---|
ILS Technical Freeze | May 20 |
Final Data Extracts | June 6 |
Migration, Mapping, Link Resolver/360/P2E Forms | June 21 |
Configuration Freeze for Alma | ~June 28 |
Cutover Start | July 3 |
Full Alma Lockout | July 8 |
Cutover Data Release/Review/Acceptance | July 21-22 |
Fulfillment Cutover (FCO)
| ~July 22-25 July 22 ~July 24-25 |
Go Live | July 26 |
Activities Overview by Phase
Onboarding | Define | Build | Deploy |
---|---|---|---|
|
|
|
|