...
Key Details
Current Phase: BuildDeploy
Go Live Date: July 26, 2022
Project Status:
Project phases: Get Ready, Onboarding, Define, Build, Deploy
Stakeholders: 18 20 participating colleges, OCLS, Ex Libris (vendor)
...
Roadmap Planner |
---|
maplinks | |
---|
timeline | true |
---|
source | %7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222021%7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222022-09-17%2000%3A00%3A00%22%2C%22endDate%22%3A%22202201%2000%3A00%3A00%22%2C%22endDate%22%3A%222022-0710-26%2000%3A00%3A00%22%2C%22displayOption%22%3A%22MONTH%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Project%20Phases%22%2C%22color%22%3A%7B%22lane%22%3A%22%23654982%22%2C%22bar%22%3A%22%238c77a1%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%22202110%2000%3A00%3A00%22%2C%22displayOption%22%3A%22WEEK%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Project%20Phases%22%2C%22color%22%3A%7B%22lane%22%3A%22%23654982%22%2C%22bar%22%3A%22%238c77a1%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222021-09-27%2010%3A27%3A19%22%2C%22id%22%3A%22e055c8a9-e070-40ef-901c-41552052c1ed%22%2C%22title%22%3A%22Onboarding%22%2C%22description%22%3A%22Oct%2029%3A%20Third%20Party%20Integ.%20Form%5CnNov%205%3A%20Draft%20Mig%2C%20Map%2C%20P2E%20form%5CnNov%2012%3A%20Final%20Mig%2C%20Map%2C%20P2E%20Form%5CnNov%2019%3A%20Final%20E-Res.%20Activation%20%26%20Authentic.%20Forms%22%2C%22duration%22%3A1%20Forms%22%2C%22duration%22%3A7.8217821782178218%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%2220229445426669973545%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222022-01-16%2000%3A57%3A01%22%2C%22id%22%3A%2228fb7d54-79c2-4c7f-b8d3-0b66d725cd11%22%2C%22title%22%3A%22Build%22%2C%22description%22%3A%22SIS%20%26%20Authentication%20Integration%20Cutover%20Survey%2FNotes%20for%20Cutover%5CnMigration%20%26%20Mapping%20Forms%5CnP2E%2C%20LinkResolver%2C%20etc.%22%2C%22duration%22%3A5%22%2C%22duration%22%3A27.584158415841584%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A4%2C%22startDate%22%3A%222022455445544554454%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A4%2C%22startDate%22%3A%222022-07-01%2007%3A21%3A58%22%2C%22id%22%3A%22187582af27%2005%3A13%3A39%22%2C%22id%22%3A%22187582af-441e-47cf-b347-6f29422a83c5%22%2C%22title%22%3A%22Deploy%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222021-6f29422a83c5%22%2C%22title%22%3A%22Deploy%22%2C%22description%22%3A%22Cutover%20%26%20Data%20Acceptance%5CnGO%20LIVE%20-%20July%2026%5CnHealth%20Checklist%20-%20due%20Aug%2026%22%2C%22duration%22%3A9.673267326732674%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222021-11-09%2020%3A51%3A40%22%2C%22id%22%3A%22f548073e-0d78-4892-acbf-39b633c9b12c%22%2C%22title%22%3A%22Define%22%2C%22description%22%3A%22Tuesdays%3A%20Weekly%20Project%20Meeting%5CnDec.%208%3A%20Draft%20Config.%20Form%20due%5CnDec.%2017%3A%20Final%20Config.%20Form%20due%5CnMore%20information%20to%20follow%22%2C%22duration%22%3A2%20Form%20due%5CnMore%20information%20to%20follow%22%2C%22duration%22%3A9.207920792079208%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22title%22%3A%22Get%20Ready%22%2C%22description%22%3A%22This%20is%20the%20first%20bar534653409391534%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22title%22%3A%22Get%20Ready%22%2C%22description%22%3A%22This%20is%20the%20first%20bar.%22%2C%22startDate%22%3A%222021-09-01%2007%3A07%3A43%22%2C%22duration%22%3A001%2007%3A07%3A43%22%2C%22duration%22%3A3.8415841584158416%2C%22rowIndex%22%3A0%2C%22id%22%3A%223ebbaa266067892493386244%2C%22rowIndex%22%3A0%2C%22id%22%3A%223ebbaa26-efb6-444a-ab53-5544b30ddeb0%22%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Current%20Status%22%2C%22markerDate%22%3A%222022-06-01%2007%3A07%3A43%22%7D%5D%7D-5544b30ddeb0%22%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A5%2C%22startDate%22%3A%222022-10-02%2020%3A40%3A23%22%2C%22id%22%3A%22b6293223-016b-4793-8910-11e2e353cf90%22%2C%22title%22%3A%22Switch%20to%20Support%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.3762376237623761%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Current%20Status%22%2C%22markerDate%22%3A%222022-10-12%2013%3A32%3A40%22%7D%5D%7D |
---|
pagelinks | |
---|
title | Roadmap%20Planner |
---|
hash | 408dbb99c91ed9d198002ad131e56e8c |
---|
|
Priority Tasks
...
Task
...
Due Date
...
Completing initial review of Mapping Form
...
May 20
...
Complete Scheduled Jobs Spreadsheet
...
May 31
Important Dates
...
Event
...
Date
...
ILS Technical Freeze
Any data changes must be complete before this date
...
May 20
...
Final Data Extracts
...
June 6
...
Migration, Mapping, Link Resolver/360/P2E Forms
...
June 21
...
Configuration Freeze for Alma
No further configuration changes in Alma
...
~June 28
...
Cutover Start
...
July 3
...
Full Alma Lockout
No access to Alma test environments - can use sandboxes
...
July 8
...
Cutover Data Release/Review/Acceptance
...
July 21-22
...
Fulfillment Cutover (FCO)
ILS Circulation Freeze/Extract
FCO Data Release/Review/Acceptance
...
~July 22-25
July 22
~July 24-25
...
Go Live
...
fb8b5a8f2de7a1bb25ea3f46ce4e20b3 |
|
Activities Overview by Phase
Onboarding | Define | Build | Deploy |
---|
| | Workflows & functional review Functional calls Advanced eLearning Alma workshop Discovery interface setup GO LIVE readiness checklist 3rd party integration set up Administration certification Library staff training CUTOVER (freeze and load)
| |