Introduction
The CLSP Page 1+ Implementation Project involves migrating participating libraries from their existing ILSs to a shared Library Services Platform (LSP), specifically Ex Libris Alma & Primo. Learn more about the project and the CLSPPage 1+.
Page Tree |
---|
root | Project Overview |
---|
startDepth | 1 |
---|
|
Key Details
Current Phase: BuildDeploy
Go Live Date: July 26, 2022
Project Status:
Project phases: Get Ready, Onboarding, Define, Build, Deploy
Stakeholders: 18 20 participating colleges, OCLS, Ex Libris (vendor)
...
Roadmap Planner |
---|
maplinks | |
---|
timeline | true |
---|
source | %7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222021%7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222022-09-17%2000%3A00%3A00%22%2C%22endDate%22%3A%22202201%2000%3A00%3A00%22%2C%22endDate%22%3A%222022-0710-26%2000%3A00%3A00%22%2C%22displayOption%22%3A%22MONTH%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Project%20Phases%22%2C%22color%22%3A%7B%22lane%22%3A%22%23654982%22%2C%22bar%22%3A%22%238c77a1%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%22202110%2000%3A00%3A00%22%2C%22displayOption%22%3A%22WEEK%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Project%20Phases%22%2C%22color%22%3A%7B%22lane%22%3A%22%23654982%22%2C%22bar%22%3A%22%238c77a1%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222021-09-27%2010%3A27%3A19%22%2C%22id%22%3A%22e055c8a9-e070-40ef-901c-41552052c1ed%22%2C%22title%22%3A%22Onboarding%22%2C%22description%22%3A%22Oct%2029%3A%20Third%20Party%20Integ.%20Form%5CnNov%205%3A%20Draft%20Mig%2C%20Map%2C%20P2E%20form%5CnNov%2012%3A%20Final%20Mig%2C%20Map%2C%20P2E%20Form%5CnNov%2019%3A%20Final%20E-Res.%20Activation%20%26%20Authentic.%20Forms%22%2C%22duration%22%3A1%20Forms%22%2C%22duration%22%3A7.8217821782178218%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%2220229445426669973545%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222022-01-16%2000%3A57%3A01%22%2C%22id%22%3A%2228fb7d54-79c2-4c7f-b8d3-0b66d725cd11%22%2C%22title%22%3A%22Build%22%2C%22description%22%3A%22Data%20Testing%5CnConfiguration%20Testing%5CnGo%20Live%20Readiness%20Checklist%5CnCutover%20Survey%2FNotes%20for%20Cutover%22%2C%22duration%22%3A50b66d725cd11%22%2C%22title%22%3A%22Build%22%2C%22description%22%3A%22SIS%20%26%20Authentication%20Integration%20Cutover%20Survey%2FNotes%20for%20Cutover%5CnMigration%20%26%20Mapping%20Forms%5CnP2E%2C%20LinkResolver%2C%20etc.%22%2C%22duration%22%3A27.584158415841584%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A4%2C%22startDate%22%3A%222022455445544554454%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A4%2C%22startDate%22%3A%222022-07-01%2007%3A21%3A58%22%2C%22id%22%3A%22187582af27%2005%3A13%3A39%22%2C%22id%22%3A%22187582af-441e-47cf-b347-6f29422a83c5%22%2C%22title%22%3A%22Deploy%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222021-6f29422a83c5%22%2C%22title%22%3A%22Deploy%22%2C%22description%22%3A%22Cutover%20%26%20Data%20Acceptance%5CnGO%20LIVE%20-%20July%2026%5CnHealth%20Checklist%20-%20due%20Aug%2026%22%2C%22duration%22%3A9.673267326732674%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222021-11-09%2020%3A51%3A40%22%2C%22id%22%3A%22f548073e-0d78-4892-acbf-39b633c9b12c%22%2C%22title%22%3A%22Define%22%2C%22description%22%3A%22Tuesdays%3A%20Weekly%20Project%20Meeting%5CnDec.%208%3A%20Draft%20Config.%20Form%20due%5CnDec.%2017%3A%20Final%20Config.%20Form%20due%5CnMore%20information%20to%20follow%22%2C%22duration%22%3A2%20Form%20due%5CnMore%20information%20to%20follow%22%2C%22duration%22%3A9.207920792079208%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22title%22%3A%22Get%20Ready%22%2C%22description%22%3A%22This%20is%20the%20first%20bar534653409391534%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22title%22%3A%22Get%20Ready%22%2C%22description%22%3A%22This%20is%20the%20first%20bar.%22%2C%22startDate%22%3A%222021-09-01%2007%3A07%3A43%22%2C%22duration%22%3A001%2007%3A07%3A43%22%2C%22duration%22%3A3.8415841584158416%2C%22rowIndex%22%3A0%2C%22id%22%3A%223ebbaa266067892493386244%2C%22rowIndex%22%3A0%2C%22id%22%3A%223ebbaa26-efb6-444a-ab53-5544b30ddeb0%22%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A5%2C%22startDate%22%3A%222022-10-5544b30ddeb0%22%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Current%20Status%22%2C%22markerDate%22%3A%22202202%2020%3A40%3A23%22%2C%22id%22%3A%22b6293223-05-05%2014%3A29%3A42%22%7D%5D%7D | pagelinks |
---|
title | Roadmap%20Planner |
---|
hash | 7054a2765142c12801933c4794ea88b6 |
---|
|
Priority Tasks
...
Task
...
Due Date
...
Complete SIS and Authentication
...
April 29
...
Confirm extract preferences for OCLS/Complete Cutover Survey
...
April 29
...
Symphony colleges - Complete Go Live Readiness Checklist
...
April 29
...
Non-Symphony colleges - Complete Go Live Readiness Checklist
...
May 10
...
Complete Scheduled Jobs Spreadsheet
...
May 31
Important Dates
...
Event
...
Date
...
ILS Technical Freeze
...
May 20
...
Final Data Extracts
...
June 6
...
Migration, Mapping, Link Resolver/360/P2E Forms
...
June 21
...
Configuration Freeze for Alma
...
~June 28
...
Cutover Start
...
July 3
...
Full Alma Lockout
...
July 8
...
Cutover Data Release/Review/Acceptance
...
July 21-22
...
Fulfillment Cutover (FCO)
ILS Circulation Freeze/Extract
FCO Data Release/Review/Acceptance
...
~July 22-25
July 22
~July 24-25
...
Go Live
...
016b-4793-8910-11e2e353cf90%22%2C%22title%22%3A%22Switch%20to%20Support%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.3762376237623761%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Current%20Status%22%2C%22markerDate%22%3A%222022-10-12%2013%3A32%3A40%22%7D%5D%7D | pagelinks | |
---|
title | Roadmap%20Planner |
---|
hash | fb8b5a8f2de7a1bb25ea3f46ce4e20b3 |
---|
|
Activities Overview by Phase
Onboarding | Define | Build | Deploy |
---|
| | Workflows & functional review Functional calls Advanced eLearning Alma workshop Discovery interface setup GO LIVE readiness checklist 3rd party integration set up Administration certification Library staff training CUTOVER (freeze and load)
| |