  • Cohort One will begin testing and troubleshooting on June 4th.

  • Cohort Two will begin testing and troubleshooting on June 26th.

  • Cohort Three will begin testing and troubleshooting on July 17th.

Preparation for Testing

  1. Ensure that you have the correct roles for performing resource sharing activities in Alma: You will need the roles of Fulfillment Services Operator or Fulfillment Services Manager role, scoped to your resource sharing library. Please refer to the configuration documentation if you need to add these roles.

  2. Prior to testing, implement the configurations for Go Live included in the configuration documentation:

...

3. Identify at least 3 items that you have made available for resource sharing requests that you will be able to use for testing. We recommend that your partner should not also have a copy of that title.

Testing

A live demonstration will be held for each cohort. Members of each cohort have been paired into testing partners based on rota. See the Cohort One Partners Table cohort partner tables below.

We recommend that you begin testing with your partner by replicating the demonstration done in the meetingshared in our previous meetings. A recording is available here:https://clo-collaboration-spaces.atlassian.net/wiki/x/AYCiVg (Minute 22:35).

The borrowing library demonstration included:

...

  • Cancelling a request

  • Rejecting a request as the borrowing library

  • Rejecting a request as the lending library

  • Placing a hold on the item

  • Renews

  • Renews when there is a second hold on the item

  • Any other tests that you would like to run

Known Issues

The RSWG identified the issues listed below during earlier testing. These are being examined by Ex Libris Support.

  • Due date: We are observing that the configurations as is calculate due date based on shipping day. We are still trying to find a combination of settings that accounts for shipping.

  • Recalls:  In order to facilitate a no recalls policy when a physical item request is placed for an item that has been loaned through a resource sharing request, the Recalled by Partner and Borrower Recall steps have been disabled in the Page 1+ Borrowing and Page 1+ Lending Workflows distributed from the Network Zone. With these steps removed from the workflow profiles, all behavior will be dictated by the normal operation of TOUs and the Loan Recall Configuration menu, as with any other kind of loan. In testing, we noticed that removing these steps from the workflow profiles preserves the due date for the item. However, renewals for the item could be blocked and the status of the item might not be changed in the borrowing or lending requests lists. Staff will be able to see the status in the history of the request.  

  • Resource sharing request and the task widget: We have observed that borrowing and lending requests are not consistently appearing on the task widget without active notes.

  • Colleges outside of the networked environment placing requests: Presently, institutions outside of the networked environment do not have access to the catalog of networked institutions. In order for an institution outside of the networked environment to have access to the catalog on a networked institution and place resource sharing requests directly from an item record in Primo VE, both institutions will need to implement deep search configurations for Primo VE. The deep search functionality is currently limited to one institution/search profile. Alternatively, patrons can place requests through the Blank ILL form in Primo VE.

Note: The Active Resource Sharing Request Limit in the Page 1+ Borrowing Rules has been changed to 10 just for testing. This limit will be changed back to 5 after testing.

Cohort One Partners

Partner 1

Partner 2

Partner 3

Algonquin

Loyalist

Georgian

Lambton

St. Clair

Conestoga

Mohawk

Niagara

Conestoga

St. Lawrence

Sheridan

George Brown

Cohort Two Partners

Partner 1

Partner 2

Partner 3

Partner 4

Fleming

La Cité

Loyalist

Fanshawe

Centennial

Humber

Conestoga

Boréal

Cambrian

Confederation

Lambton

Northern

Sault

St. Lawrence

Cohort 3 Partners

Partner 1

Partner 2

Partner 3

Partner 4

Seneca

Loyalist

Conestoga

St Lawrence

Discussion Pages

Use your college discussion page to ask questions of the RSWG members, help keep track of trouble shooting, and track issues.

...