Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  1. Islandora extracts

-BagIt is not a viable option for extracting for OCLS at this point

-OAI-PMH extracting requirements:
  a. Simple objects only (1 metadata record to 1 file)

Michelle

is confirming that all 5 sites only have 'simple' objects

As per Michelle:
"There are only 2 instances of the compound object model being used amongst all the islandora colleges, both from Conestoga, and one of them is a test object.
I've uploaded the zip export from Loyalist (PoC), another islandora college moving to Alma-D but have their own migration going on and are doing it manually it's in the testload folder"

  b. Alma migration downloads the files from the Islandora's 'front end' and so is subject to access restrictions

Michelle

will investigate if it's possible to temporarily disable all file restrictions (e.g. when the library is closed)

We may want to test this ahead of extracting.

  c. Crosswalk to MARC21 for Georgian (with OAI-PMH method)Islandora data must be in DC / QDC and likely won't include customized fields

Laura

will review the migration schedule to see what the next available test load migration dates would be available if OCLS is unable to provide all extracts by 3/15/2023 at the latest.

Meeting recording:

...

Michelle Ng (OCLS)

Idit

For the OAI-PMH test on Fleming

Repository path
https://fleming.core.ocls.ca/oai2

Repository unique identifier
fleming

Laura Pierson - ExL, Implementation Consultant

Also added Michelle's OAI-PMH-testing message for Fleming under their thread:

Re: FLEM (Islandora) - Submit to MFT Full Extracts & File Delivery List (Analysis) - OCLS - Alma-D Implementation

New boost

Mar 2

Laura Pierson - ExL,

Implementation Consultant

Michelle

and

Liana

RE: Reviewing the migration schedule to see what the next available test load migration dates would be available if OCLS is unable to provide all extracts by 3/15/2023

I checked with ExL migration management on alternative dates.
If you are unable to provide the extracts by 3/15/2023, we would be required to push the test load migration out to May 2023.

Thanks,
-Laura

New boost

Mar 5

Idit Shachar-Abutbul

I responded in the to do:
Re: FLEM (Islandora) - Submit to MFT Full Extracts & File Delivery List (Analysis) - OCLS - Alma-D Implementation