Phase

Activity

Estimated Hours to Complete Activity

Due Date

Onboarding (Sep-Dec)

Review Technical Requirements for Alma and Primo Implementation Guide. Link to Guide: https://knowledge.exlibrisgroup.com/Alma/Implementation_and_Migration/Implementation_Guides/03Technical_Requirements_for_Alma_and_Discovery_Implementation

Description: This document describes Alma cloud fundamentals, the technology driving the Alma cloud, the IT side of the Alma cloud infrastructure, and the Alma cloud's interaction with on premises institutional/campus systems.

1-5

Meeting with Library Staff and OCLS Consultants to prepare for ILS Data Extracts

1

Plan ILS data extract (Mohawk Only)

3-15

Review Integrations with External Systems: https://knowledge.exlibrisgroup.com/Alma/Implementation_and_Migration/Implementation_Tutorials/03_Alma_Integrations_with_External_Systems and discuss anticipated integrations with Library staff.

Description: The video clips provide a brief overview of Alma's integrations with various external systems, to help you decide which integrations to implement.

1-5

Review Authentication details and requirements documentation Authentication

1-5

Meeting with vendor (Ex Libris Consultants): 3rd Party Integrations Overview for College IT (Authentication & SIS)

1

TBD

Meet with Library staff to determine matching ID Authentication

2-15

Work with Library staff to complete Authentication Form Authentication

1-5

Review Student/Staff Information System Integration details and requirements documentation Student/Staff Information Systems Integration

1-5

Complete ILS data extract for Test Load (Mohawk Only)

1-3

Define (Jan-Mar)

Meeting with vendor (Ex Libris Consultants): 3rd Party Integrations Overview for College IT (Authentication & SIS) - Q&A

1

TBD

Complete Alma / Primo VE Authentication Configuration

10-30

Complete Alma SIS Testing

10-30

Build (Mar-Apr)

Complete Priority 1 3rd Party Integrations

0-20

Adjust Alma / Primo VE Authentication Configuration if necessary

0-10

Adjust Alma SIS Load Configuration if necessar

0-10

Deploy (Apr-May)

Complete ILS data extract for Cutover (Mohawk Only)

1-5

Complete ILS fulfillment data extract for Cutover (Mohawk Only)

1-5

Download PDF Copy of Schedule

View file
nameMNI-College IT Resource Schedule-2022-10-14.pdf

Additional Documentation

Link to CLSP Implementation Site with Ex Libris Data Security & Privacy Information: Ex Libris Data Security & Privacy Information

...