source | %7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222021%7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222022-0906-17%2000%3A00%3A00%22%2C%22endDate%22%3A%22202201%2000%3A00%3A00%22%2C%22endDate%22%3A%222022-0708-26%2000%3A00%3A00%22%2C%22displayOption%22%3A%22MONTH%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Project%20Phases%22%2C%22color%22%3A%7B%22lane%22%3A%22%23654982%22%2C%22bar%22%3A%22%238c77a1%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%22202130%2000%3A00%3A00%22%2C%22displayOption%22%3A%22MONTH%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Project%20Phases%22%2C%22color%22%3A%7B%22lane%22%3A%22%23654982%22%2C%22bar%22%3A%22%238c77a1%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222021-09-27%2010%3A27%3A19%22%2C%22id%22%3A%22e055c8a9-e070-40ef-901c-41552052c1ed%22%2C%22title%22%3A%22Onboarding%22%2C%22description%22%3A%22Oct%2029%3A%20Third%20Party%20Integ.%20Form%5CnNov%205%3A%20Draft%20Mig%2C%20Map%2C%20P2E%20form%5CnNov%2012%3A%20Final%20Mig%2C%20Map%2C%20P2E%20Form%5CnNov%2019%3A%20Final%20E-Res.%20Activation%20%26%20Authentic.%20Forms%22%2C%22duration%22%3A1.8217821782178218%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222022-01-16%2000%3A57%3A01%22%2C%22id%22%3A%2228fb7d54-79c2-4c7f-b8d3-0b66d725cd11%22%2C%22title%22%3A%22Build%22%2C%22description%22%3A%22SIS%20%26%20Authentication%20Integration%20Cutover%20Survey%2FNotes%20for%20Cutover%5CnMigration%20%26%20Mapping%20Forms%5CnP2E%2C%20LinkResolver%2C%20etc.%22%2C%22duration%22%3A5.584158415841584%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A4%2C%22startDate%22%3A%222022-07-01%2007%3A21%3A58%22%2C%22id%22%3A%22187582af-441e-47cf-b347-6f29422a83c5%22%2C%22title%22%3A%22Deploy%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222021-11-09%2020%3A51%3A40%22%2C%22id%22%3A%22f548073e-0d78-4892-acbf-39b633c9b12c%22%2C%22title%22%3A%22Define%22%2C%22description%22%3A%22Tuesdays%3A%20Weekly%20Project%20Meeting%5CnDec.%208%3A%20Draft%20Config.%20Form%20due%5CnDec.%2017%3A%20Final%20Config.%20Form%20due%5CnMore%20information%20to%20follow%22%2C%22duration%22%3A2.207920792079208%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22title%22%3A%22Get%20Ready%22%2C%22description%22%3A%22This%20is%20the%20first%20bar.%22%2C%22startDate%22%3A%222021-09-01%2007%3A07%3A43%22%2C%22duration%22%3A0.8415841584158416%2C%22rowIndex%22%3A0%2C%22id%22%3A%223ebbaa26-efb6-444a-ab53-5544b30ddeb0%22%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Current%20Status%22%2C%22markerDate%22%3A%222022-0607-15%2006%3A10%3A41%22%7D%5D%7D01%2000%3A00%3A01%22%7D%5D%7D |
---|
pagelinks | |
---|
title | Roadmap%20Planner |
---|
hash | c203968218aac1b853fb210e2e119c04 |
---|
|
Priority Tasks
...
Task
...
Due Date
...
Complete Draft Mapping & Migration Form
...
June 14
...
Complete Final Mapping & Migration Form
...
June 21
5ed3006cb5fd1cca8c452ed7d98f1423 |
|
Important Dates
Event | Date |
---|
ILS Technical Freeze Any data changes must be complete before this date | May 20 |
Final Data Extracts | June 6 |
Migration, Mapping, Link Resolver/360/P2E Forms | June 21 |
Configuration Freeze for Alma No further configuration changes in Alma | ~June 28 |
Cutover Start | July 3 |
Full Alma & Primo Lockout No access to Alma or Primo test environments - can use sandboxes and search in public Primo VE but result may look strange | July 8 |
Cutover Alma Data Release/Review/Acceptance | July 21-22 |
Fulfillment Cutover (FCO) | ~July 22-25 July 22~July 24- July 25 |
Cutover Primo Release/Review/Acceptance | July 25 |
Go Live | July 26 |