Roadmap Planner | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Priority Tasks
Task | Due Date |
---|---|
Completing initial review of Mapping Complete Draft Mapping & Migration Form | May 20June 14 |
Complete Scheduled Jobs SpreadsheetMay 31Final Mapping & Migration Form | June 21 |
Important Dates
Event | Date |
---|---|
ILS Technical Freeze | May 20 |
Final Data Extracts | June 6 |
Migration, Mapping, Link Resolver/360/P2E Forms | June 21 |
Configuration Freeze for Alma | ~June 28 |
Cutover Start | July 3 |
Full Alma Lockout | July 8 |
Cutover Data Release/Review/Acceptance | July 21-22 |
Fulfillment Cutover (FCO)
| ~July 22-25 July 22 ~July 24-25 |
Go Live | July 26 |
...