...
Roadmap Planner | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Priority Tasks
Task | Due Date |
---|---|
Complete SIS and Authentication | April 29 |
Confirm extract preferences for OCLS/Complete Cutover Survey | April 29|
Symphony colleges - Complete Go Live Readiness Checklist | April 29 |
Non-Symphony colleges - Complete Go Live Readiness Checklist | May 10 |
Completing data clean up/changes in current ILS | May 20 |
Complete Scheduled Jobs Spreadsheet | May 31 |
...
Event | Date |
---|---|
ILS Technical Freeze | May 20 |
Final Data Extracts | June 6 |
Migration, Mapping, Link Resolver/360/P2E Forms | June 21 |
Configuration Freeze for Alma | ~June 28 |
Cutover Start | July 3 |
Full Alma Lockout | July 8 |
Cutover Data Release/Review/Acceptance | July 21-22 |
Fulfillment Cutover (FCO)
| ~July 22-25 July 22 ~July 24-25 |
Go Live | July 26 |
...