source%7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222021-09-17%2000%3A00%3A00%22%2C%22endDate%22%3A%222022-07-26%2000%3A00%3A00%22%2C%22displayOption%22%3A%22MONTH%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Project%20Phases%22%2C%22color%22%3A%7B%22lane%22%3A%22%23654982%22%2C%22bar%22%3A%22%238c77a1%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222021-09-27%2010%3A27%3A19%22%2C%22id%22%3A%22e055c8a9-e070-40ef-901c-41552052c1ed%22%2C%22title%22%3A%22Onboarding%22%2C%22description%22%3A%22Oct%2029%3A%20Third%20Party%20Integ.%20Form%5CnNov%205%3A%20Draft%20Mig%2C%20Map%2C%20P2E%20form%5CnNov%2012%3A%20Final%20Mig%2C%20Map%2C%20P2E%20Form%5CnNov%2019%3A%20Final%20E-Res.%20Activation%20%26%20Authentic.%20Forms%22%2C%22duration%22%3A1.8217821782178218%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222022-01-16%2000%3A57%3A01%22%2C%22id%22%3A%2228fb7d54-79c2-4c7f-b8d3-0b66d725cd11%22%2C%22title%22%3A%22Build%22%2C%22description%22%3A%22Data%20Testing%5CnConfiguration%20Testing%5CnGo%20Live%20Readiness%20Checklist%5CnCutover%20Survey%2FNotes%20for%20Cutover%22%2C%22duration%22%3A50b66d725cd11%22%2C%22title%22%3A%22Build%22%2C%22description%22%3A%22SIS%20%26%20Authentication%20Integration%20Cutover%20Survey%2FNotes%20for%20Cutover%5CnMigration%20%26%20Mapping%20Forms%5CnP2E%2C%20LinkResolver%2C%20etc.%22%2C%22duration%22%3A5.584158415841584%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A4%2C%22startDate%22%3A%222022-07-01%2007%3A21%3A58%22%2C%22id%22%3A%22187582af-441e-47cf-b347-6f29422a83c5%22%2C%22title%22%3A%22Deploy%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222021-11-09%2020%3A51%3A40%22%2C%22id%22%3A%22f548073e-0d78-4892-acbf-39b633c9b12c%22%2C%22title%22%3A%22Define%22%2C%22description%22%3A%22Tuesdays%3A%20Weekly%20Project%20Meeting%5CnDec.%208%3A%20Draft%20Config.%20Form%20due%5CnDec.%2017%3A%20Final%20Config.%20Form%20due%5CnMore%20information%20to%20follow%22%2C%22duration%22%3A2.207920792079208%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22title%22%3A%22Get%20Ready%22%2C%22description%22%3A%22This%20is%20the%20first%20bar.%22%2C%22startDate%22%3A%222021-09-01%2007%3A07%3A43%22%2C%22duration%22%3A0.8415841584158416%2C%22rowIndex%22%3A0%2C%22id%22%3A%223ebbaa26-efb6-444a-ab53-5544b30ddeb0%22%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Current%20Status%22%2C%22markerDate%22%3A%222022-05-05%2014%3A29%3A42%22%7D%5D%7D11%2010%3A27%3A19%22%7D%5D%7D
pagelinks
titleRoadmap%20Planner
hash7054a2765142c12801933c4794ea88b6aecc64e8dd2f01674583f909685aa1e9

Priority Tasks

April 29

Task

Due Date

Complete SIS and Authentication

April 29

Confirm extract preferences for OCLS/Complete Cutover Survey

Symphony colleges - Complete Go Live Readiness Checklist

April 29

Non-Symphony colleges - Complete Go Live Readiness Checklist

May 10

Completing data clean up/changes in current ILS

May 20

Complete Scheduled Jobs Spreadsheet

May 31

...

Event

Date

ILS Technical Freeze
Any data changes must be complete before this date

May 20

Final Data Extracts

June 6

Migration, Mapping, Link Resolver/360/P2E Forms

June 21

Configuration Freeze for Alma
No further configuration changes in Alma

~June 28

Cutover Start

July 3

Full Alma Lockout

July 8

Cutover Data Release/Review/Acceptance

July 21-22

Fulfillment Cutover (FCO)

  • ILS Circulation Freeze/Extract

  • FCO Data Release/Review/Acceptance

~July 22-25

July 22

~July 24-25

Go Live

July 26

...