Event

Date

ILS Technical Freeze
Any data changes must be complete before this date

May 20

Final Data Extracts

June 6

Migration, Mapping, Link Resolver/360/P2E Forms

June 21

Configuration Freeze for Alma
No further configuration changes in Alma

~June 28

Cutover Start

July 3

Full Alma Lockout
No access to Alma test environments - can use sandboxes

July 8

Cutover Data Release/Review/Acceptance

July 21-22

Fulfillment Cutover (FCO)

  • ILS Circulation Freeze/Extract

  • FCO Data Release/Review/Acceptance

~July 22-25

July 22

~July 24-25

Go Live

July 26

...

Onboarding

Define

Build

Deploy

  • Project overview meeting

  • Access to Sandbox

  • Getting to Know Alma eLearning

  • 3rd party integration readiness

  • Data migration readiness

  • Kickoff meeting

  • Confirm project plan

  • Project status calls

  • Alma Essentials eLearning

  • Migration & configuration inputs

  • Migration test load

  • Environment delivery

  • Workflows & functional review

  • Functional calls

  • Advanced eLearning

  • Alma workshop

  • Discovery interface setup

  • GO LIVE readiness checklist

  • 3rd party integration set up

  • Administration certification

  • Library staff training

  • CUTOVER
    (freeze and load)

  • GO LIVE

  • Functional & project status calls

  • Switch to support readiness

  • Switch to Support

...