source%7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222021-09-17%2000%3A00%3A00%22%2C%22endDate%22%3A%222022-07-26%2000%3A00%3A00%22%2C%22displayOption%22%3A%22MONTH%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Project%20Phases%22%2C%22color%22%3A%7B%22lane%22%3A%22%23654982%22%2C%22bar%22%3A%22%238c77a1%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222021-09-27%2010%3A27%3A19%22%2C%22id%22%3A%22e055c8a9-e070-40ef-901c-41552052c1ed%22%2C%22title%22%3A%22Onboarding%22%2C%22description%22%3A%22Oct%2029%3A%20Third%20Party%20Integ.%20Form%5CnNov%205%3A%20Draft%20Mig%2C%20Map%2C%20P2E%20form%5CnNov%2012%3A%20Final%20Mig%2C%20Map%2C%20P2E%20Form%5CnNov%2019%3A%20Final%20E-Res.%20Activation%20%26%20Authentic.%20Forms%22%2C%22duration%22%3A1.8217821782178218%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A3%2C%22startDate%22%3A%222022-01-16%2000%3A57%3A01%22%2C%22id%22%3A%2228fb7d54-79c2-4c7f-b8d3-0b66d725cd11%22%2C%22title%22%3A%22Build%22%2C%22description%22%3A%22Data%20Testing%5CnConfiguration%20Testing%5CnGo%20Live%20Readiness%20Checklist%5CnCutover%20Survey%2FNotes%20for%20Cutover%22%2C%22duration%22%3A5.584158415841584%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A4%2C%22startDate%22%3A%222022-07-01%2007%3A21%3A58%22%2C%22id%22%3A%22187582af-441e-47cf-b347-6f29422a83c5%22%2C%22title%22%3A%22Deploy%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222021-11-09%2020%3A51%3A40%22%2C%22id%22%3A%22f548073e-0d78-4892-acbf-39b633c9b12c%22%2C%22title%22%3A%22Define%22%2C%22description%22%3A%22Tuesdays%3A%20Weekly%20Project%20Meeting%5CnDec.%208%3A%20Draft%20Config.%20Form%20due%5CnDec.%2017%3A%20Final%20Config.%20Form%20due%5CnMore%20information%20to%20follow%22%2C%22duration%22%3A2.207920792079208%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22title%22%3A%22Get%20Ready%22%2C%22description%22%3A%22This%20is%20the%20first%20bar.%22%2C%22startDate%22%3A%222021-09-01%2007%3A07%3A43%22%2C%22duration%22%3A0.8415841584158416%2C%22rowIndex%22%3A0%2C%22id%22%3A%223ebbaa26-efb6-444a-ab53-5544b30ddeb0%22%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Current%20Status%22%2C%22markerDate%22%3A%222022-0405-26%2013%3A04%3A09%22%7D%5D%7D05%2014%3A29%3A42%22%7D%5D%7D
pagelinks
titleRoadmap%20Planner
hash013ef0f069ea6bb7b56d1a2bacff85f07054a2765142c12801933c4794ea88b6

Priority Tasks

Task

Due Date

Complete SIS and Authentication

April 29

Confirm extract preferences for OCLS/Complete Cutover Survey

April 29

Symphony colleges - Complete Go Live Readiness Checklist

April 29

Non-Symphony colleges - Complete Go Live Readiness Checklist

May 10

Complete Scheduled Jobs Spreadsheet

May 31

Important Dates

Event

Date

ILS Technical Freeze

May 20

Final Data Extracts

June 6

Migration, Mapping, Link Resolver/360/P2E Forms

June 21

Configuration Freeze for Alma

~June 28

Cutover Start

July 3

Full Alma Lockout

July 8

Cutover Data Release/Review/Acceptance

July 21-22

Fulfillment Cutover (FCO)

  • ILS Circulation Freeze/Extract

  • FCO Data Release/Review/Acceptance

~July 22-25

July 22

~July 24-25

Go Live

July 26

...