The link above will direct to a detailed project plan of the CLSP Implementation. Our goal is to be as accurate as possible, but please note that dates and activities described in the plan are flexible. The Project Management Office will keep you informed of major changes to the plan and it will be useful to refer back regularly.

All changes made to the Project Plan document as of January 1, 2022 are recorded in the table below.

Row

Change

Notes

64

Event date changed from February 17th to the 18th

Editing error