...
Cohort 1 (May 21st to June 7th) | Cohort 2 (June 11th to June 28th) |
---|---|
Algonquin | Boréal |
Conestoga (Complete) | Cambrian |
Georgian | Canadore |
George Brown | Centennial |
Lambton (Complete) | Confederation |
Loyalist (Complete) | Fanshawe |
Mohawk | Fleming |
Niagara | Humber |
Sheridan | La Cité (TBD) |
St. Clair | Northern |
St. Lawrence (Complete) | Sault (TBD) |
Seneca |
Project Timeline
Test Pilot Project & Configuration Testing (April 19 - May 17)
Includes Lambton, St. Lawrence, Conestoga, Loyalist
First Cohort Implementation (May 21- June 7)
Intro: May 21, Configuration Setting: May 28, Testing: June 4
Second Cohort Implementation (June 11 - June 28)
Intro: June 11, Configuration Setting: June 18, Testing: June 25
Final Testing and Staff Workflow Confirmation (July 2 - July 5)
Go Live July 8th
...