  • Test Pilot Project & Configuration Testing (Now April 19 - May 17)

    • Includes Lambton, St. Lawrence, Conestoga, Loyalist

  • First Cohort Implementation (May 21- June 7)

    • Intro: May 21, Configuration Setting: May 28, Testing: June 4

  • Second Cohort Implementation (June 11 - June 28)

    • Intro: June 11, Configuration Setting: June 18, Testing: June 25

  • Final Testing and Staff Workflow Confirmation (July 2 - July 5)

  • Go Live July 8th

...